Servico | CONSTRUCAO - UBS DE APOIO - SAO DOMINGOS | 1.0 - SERVICOS PRELIMINARES 1.1 - PLACA DE OBRA = 1 unidade 1.2 - LOCACAO DE OBRA = (22,95+18,00+12,55+21,60) = 75,10 m 1.3 - DEPOSITO PROVISORIO = (3,0x2,0) = 6,0 m² 2.0 - MOVIMENTO DE TERRA PARA FUNDACOES 2.1 - ESCAVACAO MANUAL DE VALA (0,85x1,10x1,20x9) = 10,10 m³ (0,90x1,15x1,20x2) = 2,48 m³ (0,60x0,80x1,20x2) = 1,15 m³ (0,70x0,95x1,20x10) = 7,98 m³ (1,20x1,45x1,20) = 2,09 m³ (1,10x1,35x1,20) = 1,78 m³ (0,80x1,05x1,20x5) = 5,04 m³ (0,75x1,0x1,20x4) = 3,60 m³ TOTAL = 34,22 m³ 2.2 - REGULARIZACAO E COMPACTACAO - FUNDO DA VALA (0,85x1,10x9) = 8,42 m² (0,90x1,15x2) = 2,07 m² (0,60x0,80x2) = 0,96 m² (0,70x0,95x10) = 6,65 m² (1,20x1,45) = 1,74 m² (1,10x1,35) = 1,49 m² (0,80x1,05x5) = 4,20 m² (0,75x1,0x4) = 3,0 m² TOTAL = 28,53 m² 2.3 - REATERRO MANUAL DE VALAS (0,85x1,10x1,20x9) = 10,10 m³ (0,90x1,15x1,20x2) = 2,48 m³ (0,60x0,80x1,20x2) = 1,15 m³ (0,70x0,95x1,20x10) = 7,98 m³ (1,20x1,45x1,20) = 2,09 m³ (1,10x1,35x1,20) = 1,78 m³ (0,80x1,05x1,20x5) = 5,04 m³ (0,75x1,0x1,20x4) = 3,60 m³ TOTAL = 34,22 m³ 2.4 - ATERRO MANUAL - ENTRE VIGAS BALDRAMES (2,0x2,45) = 4,90 m² (2,40x2,45) = 5,88 m² (2,70x1,40) = 3,78 m² (1,70x1,40) = 2,38 m² (2,20x3,20) = 7,04 m² (1,20x2,20) = 2,64 m² (3,20x4,85) = 15,52 m² (1,20x4,85) = 5,82 m² (1,60x3,20) = 5,12 m² (3,30x3,20) = 10,56 m² (3,80x3,60) = 13,68 m² (3,10x3,60) = 11,16 m² (2,55x3,30) = 8,42 m² (1,0x1,15) = 1,15 m² (2,55x1,60) = 4,08 m² (5,05x1,20) = 6,06 m² (5,05x3,60) = 18,18 m² (3,25x1,15) = 3,74 m² (1,15x1,65) = 1,90 m² (2,0x2,80) = 5,60 m² (1,55x2,0x2) = 6,20 m² (1,60x2,80) = 4,48 m² (3,25x1,60) = 5,20 m² (3,40x4,15) = 14,11 m² (2,0x1,45) = 2,90 m² (2,0x1,30) = 2,60 m² (4,85x3,25) = 15,76 m² (4,15x2,20) = 9,13 m² (4,25x3,25) = 13,81 m² (4,0x4,15) = 16,60 m² (3,25x1,95) = 6,33 m² TOTAL = 234,73x0,40 = 93,89 m³ 3.0 - FUNDACOES 3.1 - CONCRETO ARMADO - SAPATAS 3.1.1- LASTRO DE CONCRETO (0,85x1,10x9) = 8,42 m² (0,90x1,15x2) = 2,07 m² (0,60x0,80x2) = 0,96 m² (0,70x0,95x10) = 6,65 m² (1,20x1,45) = 1,74 m² (1,10x1,35) = 1,49 m² (0,80x1,05x5) = 4,20 m² (0,75x1,0x4) = 3,0 m² TOTAL = 28,53x0,05 = 1,43 m³ 3.1.2 - FORMA DE MADEIRA Obtido atraves de software: = 30,60 m² 3.1.3 - ARMACAO CA50 - 8,0 MM Obtido atraves de software: = 25,80 KG 3.1.4 - ARMACAO CA50 - 6,3 MM Obtido atraves de software: = 195,10 KG 3.1.5 - CONCRETO BOMBEADO - FCK 30 MPA Obtido atraves de software: = 7,20 m³ 3.2 - CONCRETO ARMADO - VIGAS BALDRAMES 3.2.1 - FORMA DE MADEIRA Obtido atraves de software: = 206,60 m² 3.2.2 - ARMACAO CA50 - 6,3 MM Obtido atraves de software: = 24,90 KG 3.2.3 - ARMACAO CA50 - 8,0 MM Obtido atraves de software: = 401,00 KG 3.2.4 - ARMACAO CA50 - 10 MM Obtido atraves de software: = 11,30 KG 3.2.5 - ARMACAO CA60 - 5,0 MM Obtido atraves de software: = 179,90 KG 3.2.6 - CONCRETO BOMBEADO - FCK 30 MPA Obtido atraves de software: = 13,0 m³ 3.2.7 - IMPERMEABILIZACAO DE BALDRAMES Obtido atraves de software: = 206,60 m² 4.0 - SUPERESTRUTURA 4.1 - CONCRETO ARMADO - PILARES 4.1.1 - FORMA DE MADEIRA Obtido atraves de software: = 192,60 m² 4.1.2 - ARMACAO CA50 - 10,0 MM Obtido atraves de software: = 838,30 KG 4.1.3 - ARMACAO CA60 - 5,0 MM Obtido atraves de software: = 378,60 KG 4.1.4 - CONCRETO BOMBEADO - FCK 25 MPA Obtido atraves de software: = 10,40 m³ 4.2 - CONCRETO ARMADO - VIGAS 4.2.1 - FORMA DE MADEIRA Obtido atraves de software: = 312,0 m² 4.2.2 - ARMACAO CA50 - 6.3 MM Obtido atraves de software: = 1,0 KG 4.2.3 - ARMACAO CA50 - 8,0 MM Obtido atraves de software: = 557,0 KG 4.2.4 - ARMACAO CA50 - 10,0 MM Obtido atraves de software: = 38,40 KG 4.2.5 - ARMACAO CA50 - 12,5 MM Obtido atraves de software: = 24,40 KG 4.2.6 - ARMACAO CA60 - 5,0 MM Obtido atraves de software: = 265,90 KG 4.2.7 CONCRETO BOMBEADO FCK 25 MPA Obtido atraves de software: = 19,70 m³ 4.3 CONCRETO ARMADO LAJE MACICA 4.3.1 FORMA DE MADEIRA Obtido atraves de software: = 18,20 m² 4 | 0,5656 | R$ 738.855,09 | R$ 417.883,08 |